Do I need a Part P certificate?

Part P is the building-regulation section that covers electrical work in homes in England and Wales. Most small jobs are no longer notifiable — but the ones that are will block a sale if you cannot show the paperwork.

What Part P actually requires

Part P of Schedule 1 to the Building Regulations applies to dwellings (and to parts of buildings that share a supply with a dwelling, such as a flat above a shop). It requires that electrical installation work be designed and installed so that persons can reasonably be expected to be protected from fire and injury.

It is not a certificate you buy on its own. It is a building-regulation requirement, satisfied either by using a registered competent person who self-certifies the work, or by notifying building control before work starts.

What is notifiable (England & Wales, post-2013)

The 2013 amendments cut the notifiable list down to the higher-risk work. It is notifiable if it involves:

Outside those categories — like-for-like replacement of sockets, switches, light fittings or a broken accessory on an existing circuit — is not notifiable, though it still has to be safe and compliant with BS 7671.

Kitchens came off the notifiable list in 2013. Plenty of trade pages still say kitchen work is notifiable — that was the pre-2013 position. If a quote hinges on "Part P notification for the kitchen", ask which regulation they mean.

Two routes to compliance

RouteHow it worksWhat you end up with
Registered competent person (self-certification)Electrician is a member of a government-approved scheme (NICEIC, NAPIT, ELECSA and similar) and self-certifies notifiable workA Building Regulations Compliance Certificate from the scheme, usually by email within days; the local authority is notified for you
Building control notificationYou or your electrician notify the local authority before work starts; an inspector signs it offA building control completion certificate; expect a fee and possible inspection delays

What to keep, and why it matters at sale

Conveyancing solicitors ask for building-regulation evidence for alterations. Missing paperwork for a consumer-unit swap or a new circuit is a common cause of indemnity-insurance policies being bought at the last minute, or of a buyer renegotiating. Keep:

An EICR is a different document: it reports on the condition of the whole installation at a point in time. It does not prove that past work was notified.

DIY: legal, but narrower than people think

You may do non-notifiable work yourself if you are competent. Notifiable work is where DIY gets expensive: you cannot self-certify, so you must notify building control in advance and pay their fee — which usually costs more than hiring a registered electrician for the same job.